WYATT et al. v. MURRAY.
35058.
Breach of contract. Before Judge Heery. Savannah City Court. December 1, 1953.
GARDNER, P. J.
1. The evidence is sufficient to sustain the verdict.
2. There is no merit in the amended motion for new trial.
The plaintiff alleged that the work thus enumerated aggregated $9,953.14; and that the defendants voluntarily paid on that amount $2,000, leaving a balance due of $7,953.14.
In answering, the defendants admitted the first three paragraphs of the petition, which are merely formal, and denied that they owed the plaintiff any sum. In paragraph 4 of the answer, the defendants alleged that, when the $2,000 was paid to the plaintiff, that left only a balance of $1,575. In paragraph 5 of the answer, they alleged that the work was done by the plaintiff in a negligent and unskillful manner, and in paragraph 6 alleged that they incurred an expense of $2,134.75 for labor and material used in replastering and repainting the walls, which amount represents the maximum which the plaintiff claims is due him under the said contract in the amount of $559.75, and for this reason the defendants pray for judgment against the plaintiff in this sum.
The defendants amended the answer further by striking all of paragraph 6 and substituting a new paragraph 6, to the effect that the defendants incurred this expense of $1,234.75 for labor and materials used in replastering and repainting the house, leaving a balance of $340.25 due the plaintiff on the contract. The case proceeded to trial, and both parties introduced evidence. The jury returned a verdict for the plaintiff for $3,000. The defendants filed a motion for new trial on the statutory grounds and thereafter amended the motion, adding three special grounds. The court denied this motion, and the defendants assign error on that judgment.
1. As to the general grounds, the evidence is sufficient to sustain the verdict. We will discuss the evidence more in detail in passing upon the special grounds.
2. It is alleged in special ground 1 that the court committed reversible error because the following evidence was admitted without objection, and it was binding on the plaintiff, to the effect that the contract price for the work done was $3,575. "Received of J. L. Wyatt two thousand dollars ($2,000.00) on account of repair job at 14 West Hull St., Savannah, Ga. Balance not to exceed $1,575 when job is completed. (Signed) Ike Murray."
140 WYATT v. MURRAY. 90 Ga.
The plaintiff contended and testified under oath that the following portion of the purported receipt, "Balance not to exceed $1,575 when job is completed," was not in the receipt when the plaintiff signed it; that this portion of the receipt was forgery on the part of the defendants. Code 38-508 reads: "Receipts for money are always only prima facie evidence of payment, and may be denied or explained by parol."
The jury believed the testimony of the plaintiff rather than that of the defendants. When we review this special assignment in the light of the law, the court did not err in permitting the parties to explain the purported receipt, and it connects up the general grounds with special ground 1.
221 (3) (36 S. E. 2d 365), this court ruled as follows: "The plaintiff can not build up his case by statements or claims to the opposite party, unless they are part of the res gestae, or come under some other exception to the general rule. The letter complained of in special ground 5 contained numerous self-serving declarations and was highly prejudicial to the defendant, and the court erred in admitting the letter in evidence over the objections of the defendant." Therefore, it follows that the court did not err in excluding the defendants' Exhibit Number 3 over objections of the plaintiff to the effect that it was a selfserving declaration. This special ground is without merit.
4. Special ground 3 complains of the following excerpt from the charge of the court: "Ordinarily when one renders service, or transfers property value to another which the latter accepts, a promise is implied to pay the reasonable value thereof." The defendants assign error on this excerpt because the action in the instant case was based on an express contract, and was not a suit on an implied contract or quantum meruit, and because the instruction was improper and confusing and injected an issue which was not in the case and expressed an opinion by the court and intimation to the jury that the court felt that the plaintiff was entitled to recover, which charge Was highly improper and prejudicial to the defendants' rights. This charge was a correct one under Code 3-107. Paragraph 4 of the original petition shows that no definite amount was agreed upon. Paragraph 3 of the answer sets out that the defendants agreed to pay the plaintiff the cost of all labor and material used in the work, plus 10%, the overall cost not to exceed $3,575. The uncontradicted evidence shows that more than $3,575 for labor and material was used on the defendants' property. So the court correctly charged the provisions of Code 3-107 under the pleadings and the evidence. In this connection, we call attention to Rushing v. Jones, 68 Ga. App. 300, 302 (22 S. E. 2d 675), wherein this court said: "The jury could find that, though an express contract had been entered into for certain services, the actual services rendered by the plaintiff's intestate were in excess of those contemplated by the express contract, and accordingly the action on a quantum meruit basis would be maintainable for recovery to the extent of the services rendered in addition to, and exclusive of, those contemplated by the express contract." We do not feel that the pleadings and the evidence in the instant case set up a definite amount for which the work was to be done, yet, under the Rushing. case, the actual servIces rendered were in excess of the defendants' contention. Under the pleadings and the evidence in this case, it is evident that the minds of the parties never met as to any definite amount. We call attention to 12 Am. Jur. 505, 7, wherein the following statement is made: "It is only when parties do not expressly agree that the law interposes and raises a promise. . . . The rule that a promise by implication does not exist where the party had made an express promise is not arbitrary and inflexible. The mere fact that the parties have attempted to make an express contract but have not succeeded in making it enforceable with respect to some of its terms does not prevent the implication of a promise to pay for benefits conferred thereunder. . . . Nor is the implication of a promise necessarily precluded by the mere fact that an enforceable contract had previously been entered into by the same parties. Under some circumstances the contract may be treated as having been abrogated, and a recovery may be had on an implied promise to pay for benefits conferred thereunder. A party may be bound by an implied promise when he has made an express contract which has been rescinded or abandoned."
The evidence further shows that the original negotiations were for a definite amount of work from the final work done. The plaintiff testified: "When me and Mr. Wyatt first started on this figuring to do this work, he did not tell me that he wanted some work, brick and cement work, done." During the negotiations the plaintiff and the defendants had a disagreement With reference to the electrical work and who should do it. On the question of an implied contract to pay, we wish to call attention to 12 Am. Jur. 766, 239, wherein that authority said: "The policy of the law is to supply in contracts what is presumed to leave been inadvertently omitted by the parties, the parties being supposed to have made those stipulations which as honest, fair and just men they ought to have made. Therefore, whatever may fairly be implied from the terms or nature of an instrument is, in judgment of law, contained in it. . . . Terms are to be implied in a contract not because they are reasonable, but because they are necessarily involved in the contractual relationship so that the parties must have intended them and have only failed to express them because they are too obvious to need expression."
It is obvious from the evidence that the original contract or discussion between the parties did not contemplate all the work which was finally done, and the trial judge correctly charged on quantum meruit. Finally, we will call attention to the fact that the defendants, in their amended answer and in the evidence, admitted that the plaintiff was entitled to recover from them $340, whereas the plaintiff contended in the pleadings and in the evidence that the amount which the defendants owed was $7,953.14. Based on such pleadings, and the evidence from each of the parties, the court instructed the jury that they might render a verdict for any amount from $340 to $7,953.14. This charge was unexcepted to, and the jury under the pleadings and the evidence, and under the charge of the court (which we think was correct), returned a verdict for the plaintiff for $3,000. The jury were authorized to, and did, return a verdict for a cut-down on the plaintiff's claim and raised the defendants' claim.
The court did not err in denying the motion for new trial for any of the reasons assigned.
Judgment affirmed. Townsend and Carlisle, JJ., concur.
Myrick & Myrick, Shelby Myrick, contra.
Aaron Kravitch, for plaintiff in error.
DECIDED APRIL 15, 1954 -- REHEARING DENIED MAY 12, 1954.
Saturday May 23 03:55 EDT


This site exists because of donors like you.

Thanks!


Valid HTML 4.0!

Valid CSS!





Home - Tour - Disclaimer - Privacy - Contact Us
Copyright © 2000,2002,2004 Lawskills.com