Title 12, Chapter 5, Section 29
( 12-5-29)
(a) It shall be unlawful to use any waters of the state for the
disposal of sewage, industrial wastes, or other wastes, or to
withdraw, divert, or impound any surface waters of the state, except
in such a manner as to conform to and comply with this article and
all rules, regulations, orders, and permits established under this
article and applicable to the waters involved. (b) No person, without first securing from the division a permit,
shall: (1) Construct, install, or modify any system for disposal of
sewage, industrial wastes, or other wastes, or any extension or
addition thereto, when the disposal of the sewage, industrial
wastes, or other wastes constitutes pollution as defined in this
article; (2) Increase the volume or strength of any sewage, industrial
wastes, or other wastes in excess of permissive discharges
specified under any existing permit; or (3) Construct or use any new outlet for the discharge of any
sewage, industrial wastes, or other wastes into the waters of the
state when such discharge constitutes pollution as defined in this
article. (c) As applied to the waters of Allatoona Lake, Lake Blackshear, Lake Blue Ridge, Clarks Hill Lake, Hartwell Lake, Lake Sidney Lanier, Lake Oconee, Lake Seminole, Lake Sinclair, Richard B. Russell Lake, Walter F. George Reservoir, and West Point Lake, except as otherwise provided in the federal Clean Water Act of 1977, P.L. 95-217, as now or hereafter amended, it shall be unlawful for any person to operate or float a vessel having a marine toilet as the term is defined in Code Section 52-7-3 unless such marine toilet only discharges into a holding tank as the term is defined in Code Section 52-7-3; and it shall further be unlawful to operate or float such a vessel, whether moored or not, unless it has a certificate for such holding tank issued by the department affixed thereto. (d)(1) The director shall not authorize any new water pollution
control discharge permit which if granted would permit water drawn
from one river basin to be deposited into another river basin in
the discharge of sewerage, industrial waste, treated waste water,
or other wastes unless for both the basin of origin and receiving
river basin unless: (A) The director has assessed all waters in order to identify
those waters for which applicable effluent limitations are not
sufficiently stringent to allow such waters to meet applicable
water quality standards and has established total limitations
for the pollutants which cause the waters to fail to achieve
such water quality standards; (B) The director has established water quality standards for the nearest downstream lake as provided in Code Section 12-5-23.1; and (C) All applicable provisions of this article and all rules and
regulations promulgated pursuant to this article are met.
(2) All new permits issued after January 1, 2001, discharging in
excess of 3 million gallons per day shall be required to meet a
minimum standard of 0.30 milligrams of phosphorus per liter of
waste water. (3) The provisions of this subsection shall not apply to the
reissuance of existing permits, permits for the expansion of
existing facilities, permits for the withdrawal of water for
agricultural use, or permits for mining activities which use water
for the transportation of materials. (e) If any treatment plant is not in compliance with permit
requirements at any time between July 1, 1996, and July 1, 1997, the
division shall be authorized to decrease the permitted capacity of
such treatment plant in an amount up to 10 percent of the permitted
capacity and may issue a new permit based upon such amount of
decrease. |