Title 13, Chapter 10, Section 80
( 13-10-80)
(a) As used in this Code section, the term: (1) "Contractor" means a person having a direct contract with the
owner. (2) "Lower tier subcontractor" means a person other than a
contractor having a direct contract with a subcontractor. (3) "Owner" means the state, any county, municipal corporation,
authority, board of education, or other public board, public body,
department, agency, instrumentality, or political subdivision of
the state. (4) "Owner's authorized contract representative" means the
architect or engineer in charge of the project for the owner or
such other contract representative or officer as designated in the
contract documents as the party representing the owner's interest
regarding administration and oversight of the project. (5) "Subcontractor" means a person other than an owner having a
direct contract with the contractor. (b) In any public works construction contract entered into on or
after July 1, 2001, with an owner, as defined in paragraph (3) of
subsection (a) of this Code section, such contract shall provide for
the following: (1) After work has commenced at the construction site, progress
payments to be made on some periodic basis, and at least monthly,
based on the value of work completed as may be provided in the
contract documents plus the value of materials and equipment
suitably stored, insured, and protected at the construction site
and at the owner's discretion such materials and equipment
suitably stored, insured, and protected off site at a location
approved by the owner's authorized contract representative when
allowed by the contract documents, less retainage; and (2)(A) Retainage to a maximum of 10 percent of each progress
payment; provided, however, when 50 percent of the contract
value including change orders and other additions to the
contract value provided for by the contract documents is due and
the manner of completion of the contract work and its progress
are reasonably satisfactory to the owner's authorized contract
representative, the owner shall withhold no more retainage. At
the discretion of the owner and with the approval of the
contractor, the retainage of each subcontractor may be released
separately as the subcontractor completes his or her work. (B) If, after discontinuing the retention, the owner's
authorized contract representative determines that the work is
unsatisfactory or has fallen behind schedule, retention may be
resumed at the previous level. If retention is resumed by an
owner, the contractor and subcontractors shall be entitled to
resume withholding retainage accordingly. (C) At substantial completion of the work or such other standard
of completion as may be provided in the contract documents and
as the owner's authorized contract representative determines the
work to be reasonably satisfactory, the owner shall, within 30
days after invoice and other appropriate documentation as may be
required by the contract documents are provided, pay the
retainage to the contractor. If at that time there are any
remaining incomplete minor items, an amount equal to 200 percent
of the value of each item as determined by the owner's
authorized contract representative shall be withheld until such
item or items are completed. The reduced retainage shall be
shared by the contractor and subcontractors as their interests
may appear. (D) The contractor shall, within ten days from the contractor's
receipt of retainage from the owner, pass through payments to
subcontractors and shall reduce each subcontractor's retainage
in the same manner as the contractors retainage is reduced by
the owner; provided, however, that the value of each
subcontractor's work complete and in place equals 50 percent of
his or her subcontract value, including approved change orders
and other additions to the subcontract value, provided, further,
that the work of the subcontractor is proceeding satisfactorily
and the subcontractor has provided or provides such satisfactory
reasonable assurances of continued performance and financial
responsibility to complete his or her work including any
warranty work as the contractor in his or her reasonable
discretion may require, including, but not limited to, a payment
and performance bond. (E) The subcontractor shall, within ten days from the
subcontractor's receipt of retainage from the contractor, pass
through payments to lower tier subcontractors and shall reduce
each lower tier subcontractor's retainage in the same manner as
the subcontractors retainage is reduced by the contractor;
provided, however, that the value of each lower tier
subcontractor's work complete and in place equals 50 percent of
his or her subcontract value, including approved change orders
and other additions to the subcontract value; provided, further,
that the work of the lower tier subcontractor is proceeding
satisfactorily and the lower tier subcontractor has provided or
provides such satisfactory reasonable assurances of continued
performance and financial responsibility to complete his or her
work including any warranty work as the subcontractor in his or
her reasonable discretion may require, including, but not
limited to, a payment and performance bond. (c) This Code section shall not apply to: (1) Any contracts let by the Department of Transportation of this
state for the construction, improvement, or maintenance of roads
or highways in this state or purposes incidental thereto; or (2) Any contracts whose value or duration at the time of the award
does not exceed $150,000.00 or 45 days in duration. (d) Contract and subcontract provisions inconsistent with the
benefits extended to contractors, subcontractors, and lower tier
subcontractors by this Code section shall be unenforceable;
provided, however, that nothing in this Code section shall render
unenforceable any contract or subcontract provisions allowing
greater benefits to be extended to such contractors, subcontractors,
or lower tier subcontractors, the provisions and benefits of this
Code section being minimal only. (e) Nothing shall preclude a payor under this Code section, prior to
making a payment, from requiring the payee to submit satisfactory
evidence that all payrolls, material bills, and other indebtedness
connected with the work have been paid. |