Title 32, Chapter 2, Section 73
( 32-2-73)
The department shall be authorized to execute supplemental
agreements to the original contract covering changes or revised or
new unit prices and items and supplementing the original contract
not to exceed a 20 percent increase in cost of the project and to
execute extension agreements affecting the length of the project
which may be increased by adding sections to said project or by
relocation of said project not to exceed 20 percent of the total
length of the project or 20 percent of total contract cost. |