Title 32, Chapter 4, Section 117
( 32-4-117)
(a) A municipality may require that each bid on a particular
contract, as a prerequisite to the bid being considered, be
accompanied by a proposal guaranty in the form of a certified check
or other acceptable security payable to the municipality for an
amount deemed by the municipality in the public interest necessary
to ensure that the successful bidder will execute the contract on
which he bid. (b) Such proposal guaranty will be returned to a bidder upon receipt
by the municipality of the bidder's written withdrawal of his bid if
such receipt is before the time scheduled for the opening of bids.
Upon the determination by the municipality of the lowest reliable
bidder, the municipality will return proposal guaranties to all
bidders except the proposal guaranty of the lowest reliable bidder.
If no contract award is made within 30 days after the date set for
the opening of bids, all bids shall be rejected and all proposal
guaranties shall be returned unless the municipality and the
successful bidder agree in writing to a longer period of time. |