Title 46, Chapter 3A, Section 4
( 46-3A-4)
(a) The commission shall issue a certificate upon a finding that
there is or will be a need for the proposed capacity resource at the
time that the proposed resource is proposed to be utilized to assure
an economical and reliable supply of electric power and energy for
the Georgia retail customers of a utility, that the certificate is
required by the public convenience and necessity, and that the
certificate complies with the provisions of this chapter and the
rules of the commission. (b) The utility's application for a certificate shall be accompanied
by its current integrated resource plan, whether or not previously
filed. (c) The utility's application for a certificate shall contain a
cost-benefit analysis covering the estimated useful life of all
capacity resource options considered in developing its current
integrated resource plan. The estimated cost of the capacity
resource proposed to be certificated shall be presented in such
reasonable detail as the commission may require. |